A Photoblog of the New Building Construction


Photos from May 2018

May 2, 2018: The Q-deck is in place on the roof over the warm side of the club.

May 2, 2018: The elevator shaft has reached the second floor and the walls have been filled with cement.

May 2, 2018: The masonry workers working on the interior walls for the mechanical room, the ice makers office, and the storeroom along the east side of the building.

May 2, 2018: The scaffolding for the masonry workers along the east side.

May 2, 2018: The southeast corner of the building.

May 2, 2018: The southwest corner of the building.

May 2, 2018: The ice shed with the Q-deck in place.

May 2, 2018: The view of the west side of the building showing the patio and the back set of stairs.

May 2, 2018: They are using a pretty big Hilti gun to pin the Q-deck in place.

May 4, 2018: The Q-deck for the second floor is in place.

May 4, 2018: The view from the far end of sheet eight.

May 4, 2018: The first floor with the second-floor Q-deck in place.

May 4, 2018: The Q-deck above the patio deck is in place.

May 4, 2018: Pinning the Q-deck on the second floor.

May 4, 2018: The pins holding the Q-deck to the steel cross beams.

May 4, 2018: The walls for the rooms on the east side are still getting higher.

May 4, 2018: Installing the piping for the fire sprinklers in the ice shed.

May 5, 2018: Working on a Saturday morning to finish pinning the Q-deck before the inspection on Monday.

May 8, 2018: It looks like the east wall is almost finished.

May 9, 2018: Installing safety railings on the second floor.

May 9, 2018: Loading sheathing onto the ice shed roof.

May 9, 2018: The masonry wall on the east side.

May 9, 2018: Looking south into the mechanical room with the vestibule room in the background.

May 9, 2018: The vestibule for the compressor room.

May 9, 2018: The compressor room.

May 9, 2018: The view from sheet one.

May 10, 2018: Ready rod, hanging from the first floor ceiling. It will hold the cable trays which will carry the telecommunication and security wiring.

May 10, 2018: Fire sprinkler piping hanging under the first floor ceiling.

May 10, 2018: Installing conduit for the fire sprinkler system wiring.

May 12, 2018: The rebar and welded wire mesh for the concrete floor upstairs.

May 12, 2018: A closer look at the rebar and welded wire mesh.

May 12, 2018: The I-beam in the upstairs ceiling that will support the movable partition wall in the banquet room.

May 14, 2018: The masonry workers laying the last course of brick for the east wall of the mechanical room and the icemaker's office/workshop.

May 14, 2018: The plumber is marking out locations on the second floor.

May 15, 2018: Other than the bricks above the header for the big roll up door, the east wall is finished.

May 15, 2018: A view of the second floor from the top of the stairs at the main entrance. They are going to be pouring the contrete floor tomorrow.

May 15, 2018: The Site Superintendent, Dan King.

May 15, 2018: The work on the fire sprinklers in the first floor ceiling is progressing as they install smaller black piping, running east-west. The red couplings connect them to the larger black pipe underneath which is running north-south.

May 15, 2018: The steel stud framing has started. Piles and piles of hat track (far right), bottom U-channel (second from right) and steel stud have arrived.

May 15, 2018: Some hat track - which will hold the top of some steel studs in place - is attached to the bottom of a cross beam on the west wall.

May 16, 2018: Pouring the concrete floor upstairs.

May 16, 2018: Pumping cement up to the second floor.

May 16, 2018: Finishing the concrete floor upstairs.

May 16, 2018: The stair treads filled with cement.

May 16, 2018: Finishing the cement in the stair treads.

May 16, 2018: The pillars weren't in place when the downstairs concrete floor was poured so they couldn't pour cement over the fittings. Now that the pillars are in place, they could fill in the holes with cement.

May 16, 2018: The interior walls for the rooms on the east side are almost finished.

May 16, 2018: Looking at the south end of the compressor room.

May 16, 2018: The north end of the storeroom beside sheet one.

May 16, 2018: Installing more hat track on the east wall.

May 16, 2018: Some steel studs in the northwest corner of the first floor; where the locker rooms will be.

May 16, 2018: Some steel studs in the northwest corner of the first floor; where the locker rooms will be.

May 16, 2018: Plumbing drain pipes for the first floor restrooms.

May 16, 2018: The location of the interior walls are marked out on the first floor.

May 17, 2018: Russ Hetland's workers from Cascade Roofing (sponsor of our Tuesday Competitive League) have arrived. Which one is Adam?

May 18, 2018: The masonry workers are filling the top two courses of brick on the east-side walls with cement.

May 18, 2018: The storerooms and washrooms at the back end of the ice shed.

May 18, 2018: More steel studs are going up on the north exterior wall.

May 18, 2018: Looking at the steed studs on the north wall from inside on the bottom floor.

May 18, 2018: The view of the second floor from the northeast corner.

May 18, 2018: The view of the ice shed from the second floor behind sheet one.

May 18, 2018: Looking at the steel studs on the north wall from inside on the second floor. The covered deck is on the left.

May 18, 2018: Looking west across the covered deck.

May 18, 2018: Work on the roof continues. Photo courtesy of Dan King.

May 28, 2018: The electrician has been busy installing wiring.

May 28, 2018: They are now installing fire sprinkler piping on the second floor.

May 28, 2018: The rear walls are getting higher.

May 28, 2018: The headers for the doorways on the east side are finished.

May 28, 2018: The compressor room beside the far end of sheet one.

May 28, 2018: The mechanical room and vestibule beside sheet one.

May 28, 2018: The storeroom beside the near end of sheet one.

May 28, 2018: There are cross braces behind sheets one and eight. They have to be there to meet the new code, but they have replaced the original braces with something more visually aesthetic.

May 28, 2018: The steel studs for the railings on the deck are in place.

May 30, 2018: The openings for windows in the Pro Shop and Admin Office are in place.

May 30, 2018: The south walls are closer to being finished.

May 30, 2018: Some of the 36" ducting for the HVAC in the ice shed arrived today.

May 30, 2018: A couple of the HVAC ducting tubes are already hanging in the ice shed.

May 30, 2018: The view from the second floor from behind sheet eight.