Photos from December 2017 br> |
|
December 5, 2017: Over 25 truckloads of cement coming tomorrow. |
|
![]() |
|
December 5, 2017: The rebar along the north wall is ready for the cement pour. |
December 5, 2017: Finishing up the rebar along the east wall. |
![]() |
![]() |
December 6, 2017: Pumping cement for the footings on the north end. They were emptying a cement truck every 20 minuntes! |
|
![]() |
|
December 6, 2017: Topping up the forms along the east wall. |
|
![]() |
![]() |
December 11, 2017: The forms around the footings have been removed. |
|
![]() |
|
December 11, 2017: The footings for the wall between the ice shed and the viewing area. |
December 11, 2017: Backfilling along the north wall. |
![]() |
![]() |
December 13, 2017: The forms for the foundation wall that sits on the footings. |
December 13, 2017: Working on the rebar for the footings around the ice shed. |
![]() |
![]() |
December 15, 2017: The second big cement pour - the footings around the ice shed |
|
![]() |
|
December 15, 2017: Filling the ice shed footing forms with cement. |
December 15, 2017: Finishing the tops of the footings. |
![]() |
![]() |