A Photoblog of the New Building Construction


Photos from December 2017

December 5, 2017: Over 25 truckloads of cement coming tomorrow.

December 5, 2017: The rebar along the north wall is ready for the cement pour.

December 5, 2017: Finishing up the rebar along the east wall.

December 6, 2017: Pumping cement for the footings on the north end. They were emptying a cement truck every 20 minuntes!

December 6, 2017: Topping up the forms along the east wall.

December 11, 2017: The forms around the footings have been removed.

December 11, 2017: The footings for the wall between the ice shed and the viewing area.

December 11, 2017: Backfilling along the north wall.

December 13, 2017: The forms for the foundation wall that sits on the footings.

December 13, 2017: Working on the rebar for the footings around the ice shed.

December 15, 2017: The second big cement pour - the footings around the ice shed

December 15, 2017: Filling the ice shed footing forms with cement.

December 15, 2017: Finishing the tops of the footings.